Punjab's Algran Bridge Reopens After Nearly 3 Years, Reconnecting 100 Villages in Nangal Region
The Algran bridge over the Swan river in Punjab's Ropar district reopened for two-wheelers on Sunday, November 15, 2026, after remaining closed for nearly three years because of structural damage associated with flooding and concerns over sand mining.
The reopening has brought relief to residents of approximately 100 villages in the Nangal region who had faced prolonged difficulties travelling between their communities and neighbouring areas.
The bridge connects the Nangal region with parts of Ropar and Hoshiarpur districts. According to officials, the restored structure is expected to reopen to other categories of vehicles within a week.
Local residents celebrated the development by distributing sweets, marking the return of an important transport link that had remained unavailable since its closure in December 2023.
Originally constructed in 2002-03, the bridge measures approximately 420 metres in length. Structural damage became apparent after heavy rainfall and flooding in July 2023.
Environmental organisations and local residents had raised concerns that years of indiscriminate sand mining around the Swan river contributed to erosion near the bridge's foundations.
An inspection report submitted by the Central Pollution Control Board to the National Green Tribunal in August 2024 identified significant structural problems.
According to the report, five foundation wells had become exposed because of erosion, one bridge pillar had tilted, gaps between expansion joints had widened, and sections of the bridge slab had settled.
The inspection also found substantial erosion around four of the bridge's 14 pillars. The report stated that possible illegal mining between 2021 and 2024 could not be ruled out because relevant information had not been made available to the inspection team.
Following a safety assessment, authorities closed the bridge in December 2023 to prevent accidents. A temporary crossing was subsequently constructed, but it was repeatedly damaged or washed away during heavy rainfall and flooding.
The Punjab Public Works Department issued a tender worth Rs 17.56 crore in February 2025 for restoration of the damaged bridge. The repair work has now been completed.
The National Green Tribunal had previously questioned the progress of the investigation into alleged illegal mining near the structure and directed the Punjab Government to provide further information.
Punjab Education Minister Harjot Singh Bains, who represents the area, said the reopening fulfilled a commitment made to local residents. He added that the bridge had been strengthened to reduce the risk of future erosion-related damage.
Although two-wheeler access has resumed, motorists using larger vehicles will need to await confirmation that the bridge has been fully reopened to all traffic.